Longswamp Building Bids Total $1.02M; $1M Loan Advances
Longswamp's maintenance-building bids total $1,017,855, under a $1.5M to $2M estimate, Oct. 13 draft minutes show; a $1M debt ordinance comes next.

Bids for Longswamp Township's new municipal maintenance building total $1,017,855 for the base work plus contingencies, well under the $1.5 million to $2 million the township had expected, according to draft minutes of the supervisors' Oct. 13 meeting posted Nov. 11. The same night the board voted to have its solicitor prepare and advertise a borrowing ordinance for the project "not to exceed $1 million" and sent Chairman Don Hickman to collect proposals from lenders.
No contracts were awarded. The minutes, a draft until the board approves them, say the bid review "was conducted for discussion purposes only" and that "official contract awards are anticipated to take place at the next board meeting at the earliest." The board canceled its Oct. 27 meeting, the Nov. 10 agenda carried only a "Municipal Maintenance Building Status Update" with no award and no ordinance, and the next meeting is Tuesday, Nov. 24.
Three contracts, one open question
The project is split into three contracts, per page 2 of the minutes. Adding the base bids and contingencies across all three gives the $1,017,855 figure; counting every "add alternate," an optional extra a bidder prices separately, "the total project investment rises to $1,118,760."
Contract 1, the building and site work, drew seven bids. Peterson Builders was lowest "at a base bid and contingency total of $738,460, significantly undercutting the second-place contractor." With two add alternates, a concrete generator pad and an epoxy coating for the slab, "the total rises to $792,760." Hanover Engineering, the township's engineer, "highlighted that Peterson Builders attended the pre-bid meeting and has prior experience with the firm."
Contract 2, electrical, drew five bids, and the decision hinges "on the board's choice regarding a backup generator." Shannon A. Smith had the lowest base bid at $140,395; Berkshire Mechanical "provided the most competitive complete package, including the add alternate, at $201,931." Hickman said Public Works Superintendent Scott Miller "strongly advocates" for the generator and that he supports it.
Contract 3, mechanical, drew four bids, with KC Mechanical lowest at $139,000 before alternates or contingencies. Hanover "is currently collaborating with KC Mechanical on an ongoing project in another township."
Not in the bids: the storm-sewer, grading and paving work the township's own crew will do, for which "a precise figure for the remaining expenses is still pending," plus about $7,000 owed to Slate Structural, $7,000 to $8,000 for soil bearing tests and about $30,000 in remaining Hanover Engineering costs. The soil tests, which the Sept. 8 minutes had flagged as a possible added cost, came back clean, per verbal results reported to the board: "the compaction and footer design are adequate, eliminating the need for any structural design changes." Next, the final plans go to zoning officer Brad Pflum for permit review. The Sept. 8 minutes set a tentative construction start of April 1, 2027, and completion by the end of August 2027. Engineer Jill Smith committed to delivering PDF copies of all bid documents and "obtaining a missing alternate bid document within the next week."
A $1 million borrowing ceiling
Two motions by Vice Chairperson Mike Sacks, each seconded by Supervisor Mark Hilbert and approved by all three supervisors, set up the financing, per page 3.
The first authorizes "the chairman to obtain proposals from potential lenders for a range of loan terms," using a standardized request for rates on a 10-year term "alongside a few alternative term options for the potentially needed funds." Hickman will run the process and the proposals will be gathered privately: he "will receive a copy of the form allowing the Township to gather comparable rates without needing a formal public advertisement."
The second authorizes Solicitor Beth Kohl "to prepare and advertise a debt ordinance for the maintenance building project not to exceed $1 million." The solicitor's report says the ordinance "does not have to be number specific," but it must be advertised and enacted before any loan papers are signed, and "if the board wants to award the contracts in November, enacting the ordinance at that time would be necessary." That matches Kohl's Aug. 25 advice that the award and the debt ordinance need to line up.
The $1 million is the most the township could borrow, not a decision to borrow the whole cost. The minutes describe the lender request as covering "up to the required loan amount" and never say how much of the project the board means to finance. The ceiling sits $17,855 under the base-plus-contingency total and $118,760 under the all-alternates total, before consultant bills and in-house work; the rest would come from township cash, or the board would trim the add alternates, or raise the figure before enactment. The minutes do not say which. The September treasurer's report accepted the same night put the general fund at $3,349,496.42, per page 1.
The ceiling also reframes a September number. Hickman said Sept. 8 that he expected a rate of about 4.75 percent and that "a seven-year loan would result in monthly payments of approximately $35,000," which our October preview noted would imply borrowing roughly $2.5 million. By our arithmetic, $1 million at 4.75 percent costs about $14,000 a month over seven years and about $10,500 a month over ten. The minutes state no rate and no chosen term; the lender request asks for pricing on a 10-year loan plus alternatives, so the seven-year comparison may not be the term the board ends up with.
What has and has not happened since
The township's Oct. 27 notice deferred the building update to Nov. 10, and that agenda, which we previewed, listed the Oct. 13 minutes for approval and the status update, but no award and no debt ordinance. No Nov. 10 minutes are posted on the agendas page, so what the board did that night is not on the record. The ordinances page still tops out at Ordinance 2026-309, the data-center and solar amendment enacted Aug. 25, and a search of the Pennsylvania NewsMedia Association's public-notice database back to the Oct. 13 vote found no Longswamp debt-ordinance notice, while the same database carried South Heidelberg's and Douglass Township's debt-ordinance notices in October. The township does advertise there: the search turned up its Oct. 26 notice of a Nov. 10 supervisors' hearing at 7 p.m. and a Nov. 9 Zoning Hearing Board notice.
The fire radios, the subject of our October preview, do not appear in the Oct. 13 minutes. The Sept. 22 minutes recorded a $200,000 commitment toward Topton Fire Company radios and a county financing offer still to be finalized; the Nov. 10 agenda listed a separate "Topton Ambulance Radio Upgrade" under new business.
Also decided Oct. 13
All three supervisors were present; every motion was made by Sacks, seconded by Hilbert and passed unanimously.
- Bills of $513,648.23 for Sept. 23 through Oct. 13 were approved on a roll-call vote; the total equals the two disbursement lines and excludes the $17,870.79 in fund transfers listed beside them.
- The 2026 Volunteer Fire Relief allocation, $37,535.84, goes to Topton Fire Company.
- Ross Wolford was appointed a sewage enforcement officer, and the 2027 electronics recycling day was set for July 17, 2027.
- BSRE Holdings LLC gets a $736.48 refund on 1036 Woodside Ave., tabled in September pending exact figures. The refund follows an assessment appeal; our guide covers how those work.
- Tabled: the joint co-op resolution for a 2018 Bomag BW161ADO-5 roller, and the Historical Society sign request, "pending proposal."
- Septic pumping: in the current Cycle 3, "73 percent need to pump" before the June 30, 2027 deadline.
- Service Electric's franchise letter, which our October preview described as the board opening renewal talks, is less than that, Kohl reported: the company sent it because the law requires notice three years before renewal, and "renewal conversations can start two years from now or more."
What happens next
The board's next date is Tuesday, Nov. 24, in the lower-level meeting room at 1112 State St., Mertztown, starting with a 6 p.m. budget workshop per the township's meeting schedule; the business meeting is likely 7 p.m., the schedule's standard start. The Nov. 10 agenda's sidebar says only "November 24th, 6:00 pm," but the Oct. 13 agenda and Oct. 27 notice listed the Nov. 10 regular meeting at 6 p.m. the same way before the Nov. 10 agenda itself said 7. No Nov. 24 agenda is posted. The township office is open Monday through Thursday, 9 a.m. to 4 p.m., at 610-682-7388, per the homepage.
Corrections: corrections@berksbeat.com.
Sources
The public records this story is reported from.
- Longswamp Township Board of Supervisors draft minutes, October 13, 2026 (PDF, 4 pp.; posted Nov. 11, 2026)
- Longswamp Township: Agendas & Minutes page (newest minutes Oct. 13; newest board agenda Nov. 10)
- Longswamp Township Board of Supervisors agenda, November 10, 2026 (PDF; sidebar lists the Nov. 24 meeting at 6 p.m.)
- Longswamp Township Board of Supervisors AMENDED agenda, October 13, 2026 (PDF)
- Longswamp Township notice: October 27, 2026 meeting canceled, items deferred to Nov. 10 (PDF)
- Longswamp Township Board of Supervisors minutes, September 22, 2026 (PDF; fire radio vote, Berks County financing)
- Longswamp Township Board of Supervisors minutes, September 8, 2026 (PDF; bids due Oct. 12, 4.75 percent rate estimate)
- Longswamp Township Board of Supervisors minutes, August 25, 2026 (PDF; solicitor on aligning the award with a debt ordinance)
- Longswamp Township 2026 meeting schedule (budget workshops at 6 p.m.; business meetings generally 7 p.m.)
- Longswamp Township: Ordinances & Resolutions page (newest entry Ordinance 2026-309)
- Longswamp Township homepage (office address, hours, phone)